Battery Storage

Port of Tyne

Port of Tyne, Tyne Dock, South Shields, Tyne & Wear, Tyne and Wear, NE34 9PT

Port of Tyne is a 35 MW battery storage project in North East. The applicant or operator on record is Foresight. It is recorded as operational since July 2018. The determining authority is South Tyneside, reference ST/0867/16/FUL.…

Operational Β· Since 2018
Project stageOperating
  1. PlanningSep 2016 (completed)
  2. Consented (completed)
  3. ConstructionApr 2018 (completed)
  4. OperatingJul 2018 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2019-05-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

35.000 MW
Power Capacity
2018
Commissioned

πŸ“‹ Project Overview

Port of Tyne is a 35 MW battery storage project in North East. The applicant or operator on record is Foresight. It is recorded as operational since July 2018. The determining authority is South Tyneside, reference ST/0867/16/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)35.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperForesight
Owner / operatorForesight
Construction started2018
Commissioned / target2018
LocationPort of Tyne, Tyne Dock, South Shields, Tyne & Wear, Tyne and Wear, NE34 9PT
RegionNorth East
Coordinates54.9772663Β°N, 1.4559135Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2016-09-07
2018-04-01
2018-07-01