Plymouth Stor Generation - Battery storage

Plymouth Stor Generation, Faraday Road, Plymouth, Devon, PL4 0ST

Plymouth Stor Generation - Battery storage is a 20 MW battery storage project in South West. The applicant or operator on record is Pulse Clean Energy. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Plymouth, re…

Consented / Approved
Project stageConsented
  1. PlanningJan 2025 (completed)
  2. ConsentedMar 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-04-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Power Capacity

πŸ“‹ Project Overview

Plymouth Stor Generation - Battery storage is a 20 MW battery storage project in South West. The applicant or operator on record is Pulse Clean Energy. Planning permission has been granted as of March 2025 and it is awaiting construction. The determining authority is Plymouth, reference 24/01681/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW
Battery chemistryCo-located with fossil fuel plant

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPulse Clean Energy
Owner / operatorPulse Clean Energy
Year consented2025
LocationPlymouth Stor Generation, Faraday Road, Plymouth, Devon, PL4 0ST
RegionSouth West
Coordinates50.3678027Β°N, 4.1125361Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (Old REPD Ref) 10432

πŸ“… Project Timeline

2025-01-10
2025-03-26