Unit 114 & Unit 116, Pinnacle Storage Park, Adj Jubilee House, Cat & Fiddle Lane, Dale Abbey,, Derbyshire, DE7 6HE
Pinnacle Storage Park, Dale Abbey - Solar PV Panels is a 1 MW solar farm project in East Midlands. The applicant or operator on record is Hansteen Property Investments. It is recorded as under construction since January 2023. The determining authority is Erewash, reference 0322/0β¦
Under Construction
Project stageUnder construction
PlanningMar 2022 (completed)
ConsentedJul 2022 (completed)
ConstructionJan 2023 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2022-04-19.
Registered planning capacity; not measured generation.
Pinnacle Storage Park, Dale Abbey - Solar PV Panels is a 1 MW solar farm project in East Midlands. The applicant or operator on record is Hansteen Property Investments. It is recorded as under construction since January 2023. The determining authority is Erewash, reference 0322/0080.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Hansteen Property Investments
Owner / operator
Hansteen Property Investments
Year consented
2022
Construction started
2023
Location
Unit 114 & Unit 116, Pinnacle Storage Park, Adj Jubilee House, Cat & Fiddle Lane, Dale Abbey,, Derbyshire, DE7 6HE