Pinkworthy Farm, Pyworthy - Battery Storage is a 50 MW battery storage project in South West. The applicant or operator on record is Private Developer. The scheme is currently in the planning system, submitted March 2023. The determining authority is Torridge, reference 1/0146/20…

Revised
Project stageSuperseded by a new application
  1. PlanningMar 2023 (completed)
  2. Superseded by a new application (project stopped here)
  3. ConsentedAug 2024 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2024-03-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Pinkworthy Farm, Pyworthy - Battery Storage is a 50 MW battery storage project in South West. The applicant or operator on record is Private Developer. The scheme is currently in the planning system, submitted March 2023. The determining authority is Torridge, reference 1/0146/2023/OUT.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPrivate Developer
Owner / operatorPrivate Developer
Year consented2024
LocationPinkworthy Farm Pyworthy, Devon, EX22 6LQ
RegionSouth West
Coordinates50.7801941Β°N, 4.432952Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (New REPD Ref)16068

πŸ“… Project Timeline

2023-03-15