Pershore Lane, Tibberton - Battery Energy Storage System

Pershore Lane, Tibberton, Worcester, Worcestershire, WR4 0AA

Pershore Lane, Tibberton - Battery Energy Storage System is a 14 MW battery storage project in West Midlands. The applicant or operator on record is Sirius Renewable Energy. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining a…

Consented / Approved
Project stageConsented
  1. PlanningDec 2022 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2023-10-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

14.000 MW
Power Capacity

πŸ“‹ Project Overview

Pershore Lane, Tibberton - Battery Energy Storage System is a 14 MW battery storage project in West Midlands. The applicant or operator on record is Sirius Renewable Energy. Planning permission has been granted as of October 2023 and it is awaiting construction. The determining authority is Wychavon, reference W/22/02717/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)14.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSirius Renewable Energy
Owner / operatorSirius Renewable Energy
Year consented2023
LocationPershore Lane, Tibberton, Worcester, Worcestershire, WR4 0AA
RegionWest Midlands
Coordinates52.2162971Β°N, 2.1538749Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-12-22