πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Penstone Lane, Penn 1 - Battery Storage Facility

Field At (Penn 1) Penstone Lane Lower Penn, Staffordshire, WV4 4XD

Penstone Lane, Penn 1 - Battery Storage Facility is a 50 MW battery storage project in West Midlands. The applicant or operator on record is Anglo Renewables Limited. Planning permission has been granted as of September 2022 and it is awaiting construction. The determining author…

Consented / Approved
Project stageConsented
  1. PlanningFeb 2022 (completed)
  2. ConsentedSep 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-03-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity

πŸ“‹ Project Overview

Penstone Lane, Penn 1 - Battery Storage Facility is a 50 MW battery storage project in West Midlands. The applicant or operator on record is Anglo Renewables Limited. Planning permission has been granted as of September 2022 and it is awaiting construction. The determining authority is South Staffordshire, reference 22/00044/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperAnglo Renewables Limited
Owner / operatorAnglo Renewables Limited
Year consented2022
LocationField At (Penn 1) Penstone Lane Lower Penn, Staffordshire, WV4 4XD
RegionWest Midlands
Coordinates52.5603224Β°N, 2.2063671Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-02-18
2022-09-28