Land north of the A465 Heads of the Valleys road, north-west of the small town of Rhymney and north-east of Merthyr Tydfil, Mid Glamorgan
Pen March Wind Farm is a 30 MW onshore wind project in Wales. The applicant or operator on record is RWE Renewables UK Limited. The planning application was refused. The determining authority is Welsh Government (NSIP), reference DNS/3253147.β¦
Refused
Project stageRefused
PlanningOct 2023 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2025-05-06.
Registered planning capacity; not measured generation.
Pen March Wind Farm is a 30 MW onshore wind project in Wales. The applicant or operator on record is RWE Renewables UK Limited. The planning application was refused. The determining authority is Welsh Government (NSIP), reference DNS/3253147.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
30.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
RWE Renewables UK Limited
Owner / operator
RWE Renewables UK Limited
Location
Land north of the A465 Heads of the Valleys road, north-west of the small town of Rhymney and north-east of Merthyr Tydfil, Mid Glamorgan