Meaux, Wawne, Beverley, East Riding of Yorkshire, HU17 9SS
Peartree Hill Solar Farm is a 320 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is JBM Solar / RWE. Planning permission has been granted as of July 2026 and it is awaiting construction. The determining authority is The Planning Inspectorate - β¦
Consented / Approved
Project stageConsented
PlanningFeb 2025 (completed)
ConsentedJul 2026 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-07-13.
Registered planning capacity; not measured generation.
Peartree Hill Solar Farm is a 320 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is JBM Solar / RWE. Planning permission has been granted as of July 2026 and it is awaiting construction. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010157.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
320.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
JBM Solar / RWE
Owner / operator
JBM Solar / RWE
Year consented
2026
Location