Patch Elm Lane Rangeworthy, Gloucestershire, BS37 7LT
Patch Elm Lane - Battery Storage is a 35 MW battery storage project in South West. The applicant or operator on record is Green Frog Ventures Limited. Planning permission has been granted as of March 2022 and it is awaiting construction. The determining authority is South Gloucesβ¦
Consented / Approved
Project stageConsented
PlanningNov 2021 (completed)
ConsentedMar 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-03-30.
Registered planning capacity; not measured generation.
Patch Elm Lane - Battery Storage is a 35 MW battery storage project in South West. The applicant or operator on record is Green Frog Ventures Limited. Planning permission has been granted as of March 2022 and it is awaiting construction. The determining authority is South Gloucestershire, reference P21/07489/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
35.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Green Frog Ventures Limited
Owner / operator
Green Frog Ventures Limited
Year consented
2022
Location
Patch Elm Lane Rangeworthy, Gloucestershire, BS37 7LT