Land At Parc Stormy, Stormy Down, Pyle, Bridgend, Mid Glamorgan, CF33 4RS
Parc Stormy, Stormy Down is a 2.5 MW onshore wind project in Wales. The applicant or operator on record is Cenin Renewables. It is recorded as operational. The determining authority is Bridgend, reference P/15/868/FUL.β¦
Operational
Project stageOperating
PlanningJan 2016 (completed)
ConsentedAug 2016 (completed)
ConstructionNov 2019 (completed)
Operating (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2020-07-27.
Registered planning capacity; not measured generation.
Parc Stormy, Stormy Down is a 2.5 MW onshore wind project in Wales. The applicant or operator on record is Cenin Renewables. It is recorded as operational. The determining authority is Bridgend, reference P/15/868/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Cenin Renewables
Owner / operator
Cenin Renewables
Year consented
2016
Construction started
2019