Outwood Farm (Phase 2) is a 7 MW solar farm project in Eastern. The applicant or operator on record is Wirsol. Planning permission has been granted as of December 2014 and it is awaiting construction. The determining authority is Basildon, reference 14/00948/FULL.…

Consented / Approved
Project stageConsented
  1. PlanningAug 2014 (completed)
  2. ConsentedDec 2014 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2020-01-24.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

7.000 MW
Registered Capacity

πŸ“‹ Project Overview

Outwood Farm (Phase 2) is a 7 MW solar farm project in Eastern. The applicant or operator on record is Wirsol. Planning permission has been granted as of December 2014 and it is awaiting construction. The determining authority is Basildon, reference 14/00948/FULL.

Site Schematic

SUBSTATION ? ha Β· 7 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)7.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWirsol
Owner / operatorWirsol
Year consented2014
LocationLand At Outwood Farm Road Billericay, Essex, Essex
RegionEastern
Coordinates51.6218972Β°N, 0.4466912Β°E

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)246000

πŸ“… Project Timeline

2014-08-07
2014-12-11