Orton Park Farm, Orton Park, Carlisle, Cumbria, CA5 6JU
Orton Park Farm is a 1.6 MW onshore wind project in North West. The applicant or operator on record is Orton Park Wind Energy. It is recorded as operational since June 2017. The determining authority is Cumberland, reference 13/0323.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningApr 2013 (completed)
ConsentedJul 2013 (completed)
ConstructionJun 2016 (completed)
OperatingJun 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-07-12.
Registered planning capacity; not measured generation.
Orton Park Farm is a 1.6 MW onshore wind project in North West. The applicant or operator on record is Orton Park Wind Energy. It is recorded as operational since June 2017. The determining authority is Cumberland, reference 13/0323.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.600 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Orton Park Wind Energy
Owner / operator
Orton Park Wind Energy
Year consented
2013
Construction started
2016
Commissioned / target
2017
Location
Orton Park Farm, Orton Park, Carlisle, Cumbria, CA5 6JU