High Marnham, The border of Nottinghamshire, Newark, Nottinghamshire, NG23 6SF
One Earth Solar Farm is a 740 MW solar farm project in East Midlands. The applicant or operator on record is Orsted UK Limited / PS Renewables. Planning permission has been granted as of July 2026 and it is awaiting construction. The determining authority is The Planning Inspectoβ¦
Consented / Approved
Project stageConsented
PlanningFeb 2025 (completed)
ConsentedJul 2026 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-07-13.
Registered planning capacity; not measured generation.
One Earth Solar Farm is a 740 MW solar farm project in East Midlands. The applicant or operator on record is Orsted UK Limited / PS Renewables. Planning permission has been granted as of July 2026 and it is awaiting construction. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010159.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
740.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Orsted UK Limited / PS Renewables
Owner / operator
Orsted UK Limited / PS Renewables
Year consented
2026
Location
High Marnham, The border of Nottinghamshire, Newark, Nottinghamshire, NG23 6SF