Agricultural Field Circa 600M South Of Earthcott Green And Circa 297M East Of The B4427, Gloucestershire, BS35 3TD
Old Green Farm, Alveston Battery Storage is a 10 MW battery storage project in South West. The applicant or operator on record is Ecotricity. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is South Gloucestershiβ¦
Consented / Approved
Project stageConsented
PlanningApr 2017 (completed)
ConsentedNov 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2020-08-03.
Registered planning capacity; not measured generation.
Old Green Farm, Alveston Battery Storage is a 10 MW battery storage project in South West. The applicant or operator on record is Ecotricity. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is South Gloucestershire, reference PT17/1992/RVC.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
10.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Ecotricity
Owner / operator
Ecotricity
Year consented
2019
Location
Agricultural Field Circa 600M South Of Earthcott Green And Circa 297M East Of The B4427, Gloucestershire, BS35 3TD