W/O Old Chalk Pit, West Back Side, Haisthorpe, Driffield, East Riding of Yorkshire, YO25 4NW
Old Chalk Pit, West Back Side - Three Oaks Renewable Park is a 39 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Ridge Clean Energy Limited. Planning permission has been granted as of March 2024 and it is awaiting construction. The determiniβ¦
Consented / Approved
Project stageConsented
PlanningOct 2022 (completed)
ConsentedMar 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-02-20.
Registered planning capacity; not measured generation.
Old Chalk Pit, West Back Side - Three Oaks Renewable Park is a 39 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Ridge Clean Energy Limited. Planning permission has been granted as of March 2024 and it is awaiting construction. The determining authority is East Riding of Yorkshire, reference 22/02777/STPLF.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
39.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Ridge Clean Energy Limited
Owner / operator
Ridge Clean Energy Limited
Year consented
2024
Location
W/O Old Chalk Pit, West Back Side, Haisthorpe, Driffield, East Riding of Yorkshire, YO25 4NW