Operational Β· Since 2006
Project stageOperating
  1. PlanningSep 2004 (completed)
  2. ConsentedJan 2005 (completed)
  3. ConstructionMay 2006 (completed)
  4. OperatingDec 2006 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2009-06-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.000 MW
Registered Capacity
2006
Commissioned

πŸ“‹ Project Overview

Oatslie Landfill Gas is a 2 MW bioenergy / waste project in Scotland. The applicant or operator on record is Waste Recycling Group. It is recorded as operational since December 2006. The determining authority is Midlothian, reference 04/00694/FUL.

πŸ”§ Technical Specifications

Capacity (MW)2.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWaste Recycling Group
Owner / operatorWaste Recycling Group
Year consented2005
Construction started2006
Commissioned / target2006
LocationNear Roslin, Lothian
RegionScotland
Coordinates55.8555744Β°N, 3.1645028Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2004-09-01
2005-01-10
2006-05-01