Land South West of Cowley Subs, Nuneham Courtenay, Oxford,, Oxfordshire, OX44 9PA
Nuneham Courtenay Solar Farm & Battery Storage Facility is a 49.9 MW solar farm project in South East. The applicant or operator on record is Enso Energy (Cowley Baldon Green Limited). Planning permission has been granted as of January 2022 and it is awaiting construction. The deβ¦
Consented / Approved
Project stageConsented
PlanningNov 2020 (completed)
ConsentedJan 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-01-19.
Registered planning capacity; not measured generation.
Nuneham Courtenay Solar Farm & Battery Storage Facility is a 49.9 MW solar farm project in South East. The applicant or operator on record is Enso Energy (Cowley Baldon Green Limited). Planning permission has been granted as of January 2022 and it is awaiting construction. The determining authority is South Oxfordshire, reference P20/S4360/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Enso Energy (Cowley Baldon Green Limited)
Owner / operator
Enso Energy (Cowley Baldon Green Limited)
Year consented
2022
Location
Land South West of Cowley Subs, Nuneham Courtenay, Oxford,, Oxfordshire, OX44 9PA