Northampton General Hospital is a 1.9 MW bioenergy / waste project in East Midlands. The applicant or operator on record is Northampton General Hospital. It is recorded as operational since March 2016. The determining authority is West Northamptonshire, reference N/2014/0546.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningMay 2014 (completed)
  2. ConsentedJun 2014 (completed)
  3. ConstructionMar 2015 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-03-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.900 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Northampton General Hospital is a 1.9 MW bioenergy / waste project in East Midlands. The applicant or operator on record is Northampton General Hospital. It is recorded as operational since March 2016. The determining authority is West Northamptonshire, reference N/2014/0546.

πŸ”§ Technical Specifications

Capacity (MW)1.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNorthampton General Hospital
Owner / operatorNorthampton General Hospital
Year consented2014
Construction started2015
Commissioned / target2016
LocationNorthampton General Hospital Trust, Cliftonville, Northampton,, Northamptonshire, NN1 5BD
RegionEast Midlands
Coordinates52.236485Β°N, 0.8819295Β°W

Additional published register fields

Registered technologyBiomass (dedicated)

πŸ“… Project Timeline

2014-05-12
2014-06-30
2015-03-01
2016-03-01