North Yard EfW is a 22.5 MW bioenergy / waste project in South West. The applicant or operator on record is MVV Environment. It is recorded as operational since April 2015. The determining authority is Plymouth, reference 11/00750/FUL.…

Operational Β· Since 2015
Project stageOperating
  1. PlanningMay 2011 (completed)
  2. ConsentedFeb 2012 (completed)
  3. ConstructionMar 2012 (completed)
  4. OperatingApr 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-11-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

22.500 MW
Registered Capacity
2015
Commissioned

πŸ“‹ Project Overview

North Yard EfW is a 22.5 MW bioenergy / waste project in South West. The applicant or operator on record is MVV Environment. It is recorded as operational since April 2015. The determining authority is Plymouth, reference 11/00750/FUL.

πŸ”§ Technical Specifications

Capacity (MW)22.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperMVV Environment
Owner / operatorMVV Environment
Year consented2012
Construction started2012
Commissioned / target2015
LocationLand at North Year, H. M. Naval Base Devenport, Close to Weston Mill Creek and Viaduct, Plymouth, Devon, PL2 2DQ
RegionSouth West
Coordinates50.397056Β°N, 4.1848533Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2011-05-10
2012-02-03
2012-03-01