S/O North Tawton Primary Substation, North Tawton, Devon, EX20 2DA
North Tawton Primary Substation - Battery Storage is a 30 MW battery storage project in South West. The applicant or operator on record is Balance Power Projects Limited. Planning permission has been granted as of November 2021 and it is awaiting construction. The determining autβ¦
Consented / Approved
Project stageConsented
PlanningJun 2021 (completed)
ConsentedNov 2021 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2021-11-29.
Registered planning capacity; not measured generation.
North Tawton Primary Substation - Battery Storage is a 30 MW battery storage project in South West. The applicant or operator on record is Balance Power Projects Limited. Planning permission has been granted as of November 2021 and it is awaiting construction. The determining authority is West Devon, reference 2094/21/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
30.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Balance Power Projects Limited
Owner / operator
Balance Power Projects Limited
Year consented
2021
Location
S/O North Tawton Primary Substation, North Tawton, Devon, EX20 2DA