North Redbog
Strichen
Aberdeenshire
AB43 6RQ, Grampian
North Red Bog is a 1.6 MW onshore wind project in Scotland. The applicant or operator on record is Green Cat Renewables. It is recorded as operational since June 2008. The determining authority is Aberdeenshire, reference APP/2007/2794.β¦
OperationalΒ· Since 2008
Project stageOperating
PlanningJul 2007 (completed)
ConsentedMar 2008 (completed)
Construction (completed)
OperatingJun 2008 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2009-10-05.
Registered planning capacity; not measured generation.
North Red Bog is a 1.6 MW onshore wind project in Scotland. The applicant or operator on record is Green Cat Renewables. It is recorded as operational since June 2008. The determining authority is Aberdeenshire, reference APP/2007/2794.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.600 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Green Cat Renewables
Owner / operator
Green Cat Renewables
Year consented
2008
Commissioned / target
2008