North London Heat and Power (Edmonton EcoPark Replacement) is a 70 MW bioenergy / waste project in London. The applicant or operator on record is North London Waste Authority (NLWA). It is recorded as under construction since October 2022. The determining authority is The Plannin…

Under Construction
Project stageUnder construction
  1. PlanningNov 2015 (completed)
  2. ConsentedFeb 2017 (completed)
  3. ConstructionOct 2022 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-07-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

70.000 MW
Registered Capacity

πŸ“‹ Project Overview

North London Heat and Power (Edmonton EcoPark Replacement) is a 70 MW bioenergy / waste project in London. The applicant or operator on record is North London Waste Authority (NLWA). It is recorded as under construction since October 2022. The determining authority is The Planning Inspectorate - National Infrastructure, reference EN010071.

πŸ”§ Technical Specifications

Capacity (MW)70.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNorth London Waste Authority (NLWA)
Owner / operatorNorth London Waste Authority (NLWA)
Year consented2017
Construction started2022
LocationLondon Waste EcoPark, Edmonton, London, N18 3AF
RegionLondon
Coordinates51.6121255Β°N, 0.0456113Β°W

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2015-11-11
2017-02-24
2022-10-01