πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Next Distribution Centre Doncaster

Lincolnshire Way, Armthorpe, Doncaster, South Yorkshire, DN3 3FF

Next Distribution Centre Doncaster is a 2.5 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Next/ Eneco. It is recorded as operational since December 2016. The determining authority is Doncaster.…

Operational Β· Since 2016
Project stageOperating
  1. Planning (completed)
  2. Consented (completed)
  3. ConstructionNov 2016 (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-06-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

2.500 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Next Distribution Centre Doncaster is a 2.5 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Next/ Eneco. It is recorded as operational since December 2016. The determining authority is Doncaster.

Site Schematic

SUBSTATION ? ha Β· 2.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)2.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNext/ Eneco
Owner / operatorNext/ Eneco
Construction started2016
Commissioned / target2016
LocationLincolnshire Way, Armthorpe, Doncaster, South Yorkshire, DN3 3FF
RegionYorkshire and Humber
Coordinates53.5379557Β°N, 1.0334783Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarRoof

πŸ“… Project Timeline

2016-11-01
2016-12-01