New Rides Farm, Leysdown Road, Sheerness, Kent, ME12 4DD
New Rides Wind Farm is a 8.8 MW onshore wind project in South East. The applicant or operator on record is Airvolution Energy. It is recorded as operational since December 2018. The determining authority is Swale, reference SW/13/1571.β¦
OperationalΒ· Since 2018
Project stageOperating
PlanningJan 2014 (completed)
ConsentedAug 2017 (completed)
ConstructionJun 2018 (completed)
OperatingDec 2018 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2019-05-29.
Registered planning capacity; not measured generation.
New Rides Wind Farm is a 8.8 MW onshore wind project in South East. The applicant or operator on record is Airvolution Energy. It is recorded as operational since December 2018. The determining authority is Swale, reference SW/13/1571.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
8.800 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Airvolution Energy
Owner / operator
Airvolution Energy
Year consented
2017
Construction started
2018
Commissioned / target
2018
Location
New Rides Farm, Leysdown Road, Sheerness, Kent, ME12 4DD