New Rendy Farm is a 4.8 MW solar farm project in South West. The applicant or operator on record is TGC Renewables. It is recorded as operational since December 2013. The determining authority is Somerset, reference 27/13/0003.β¦
OperationalΒ· Since 2013
Project stageOperating
PlanningMar 2013 (completed)
ConsentedMay 2013 (completed)
Construction (completed)
OperatingDec 2013 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2014-03-24.
Registered planning capacity; not measured generation.
New Rendy Farm is a 4.8 MW solar farm project in South West. The applicant or operator on record is TGC Renewables. It is recorded as operational since December 2013. The determining authority is Somerset, reference 27/13/0003.