Network House, Middleton Grove, Beeston, Leeds, West Yorkshire, LS11 5PX
Network House, Beeston - Solar Panels is a 0.41 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Columbia Threadneedle Investments. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authorβ¦
Consented / Approved
Project stageConsented
PlanningOct 2023 (completed)
ConsentedJan 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2024-01-16.
Registered planning capacity; not measured generation.
Network House, Beeston - Solar Panels is a 0.41 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Columbia Threadneedle Investments. Planning permission has been granted as of January 2024 and it is awaiting construction. The determining authority is Leeds, reference 23/06002/DPD.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.410 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Columbia Threadneedle Investments
Owner / operator
Columbia Threadneedle Investments
Year consented
2024
Location
Network House, Middleton Grove, Beeston, Leeds, West Yorkshire, LS11 5PX