400 Metres North East Of Glenview Caplaw Road Neilston, Renfrewshire, PA2 8UL

Neilston - Battery Storage is a 150 MW battery storage project in Scotland. The applicant or operator on record is Apatura (GPC 1119 Ltd). Planning permission has been granted as of February 2025 and it is awaiting construction. The determining authority is Scottish Government (S…

Consented / Approved
Project stageConsented
  1. PlanningDec 2023 (completed)
  2. ConsentedFeb 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-09-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

150.000 MW
Power Capacity

πŸ“‹ Project Overview

Neilston - Battery Storage is a 150 MW battery storage project in Scotland. The applicant or operator on record is Apatura (GPC 1119 Ltd). Planning permission has been granted as of February 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004868.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)150.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperApatura (GPC 1119 Ltd)
Owner / operatorApatura (GPC 1119 Ltd)
Year consented2025
Location400 Metres North East Of Glenview Caplaw Road Neilston, Renfrewshire, PA2 8UL
RegionScotland
Coordinates55.8012839Β°N, 4.4857567Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-12-21