South Of Wakefield B Substation And East Of Neil Fox Way, West Yorkshire, WF1 5DB

Neil Fox Way - Battery Storage is a 99.9 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Wakefield, reference X47…

In Planning
Project stageIn planning
  1. PlanningAug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2025-09-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

99.900 MW
Power Capacity

πŸ“‹ Project Overview

Neil Fox Way - Battery Storage is a 99.9 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Wakefield, reference X4725/W/25/3368025.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)99.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperHarmony Energy Limited
Owner / operatorHarmony Energy Limited
LocationSouth Of Wakefield B Substation And East Of Neil Fox Way, West Yorkshire, WF1 5DB
RegionYorkshire and Humber
Coordinates53.6699605Β°N, 1.4688326Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (Old REPD Ref) 11519

πŸ“… Project Timeline

2025-08-11