Solar Farm

Naburn Sewage Treatment Works

Sewage Works, Naburn Lane, Naburn, York, North Yorkshire, YO19 4RN

Naburn Sewage Treatment Works is a 1.4 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Kelda Energy. The planning application was refused. The determining authority is York, reference 15/01845/FULM.…

Refused
Project stageRefused
  1. PlanningAug 2015 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2016-01-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.400 MW
Registered Capacity

πŸ“‹ Project Overview

Naburn Sewage Treatment Works is a 1.4 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is Kelda Energy. The planning application was refused. The determining authority is York, reference 15/01845/FULM.

Site Schematic

SUBSTATION ? ha Β· 1.4 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKelda Energy
Owner / operatorKelda Energy
LocationSewage Works, Naburn Lane, Naburn, York, North Yorkshire, YO19 4RN
RegionYorkshire and Humber
Coordinates53.9139441Β°N, 1.0853361Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)35000

πŸ“… Project Timeline

2015-08-26