Land 1740M NE Of Munerigie Munerigie Invergarry, Highland, IV63 7YN
Munerigie HydroPower Scheme is a 1 MW conventional hydro project in Scotland. The applicant or operator on record is Renewable Design & Development Limited. The planning permission has expired. The determining authority is Highland, reference 14/01222/FUL.β¦
Expired
Project stageConsent lapsed
PlanningApr 2014 (completed)
ConsentedJun 2014 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2019-11-20.
Registered planning capacity; not measured generation.
Munerigie HydroPower Scheme is a 1 MW conventional hydro project in Scotland. The applicant or operator on record is Renewable Design & Development Limited. The planning permission has expired. The determining authority is Highland, reference 14/01222/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Renewable Design & Development Limited
Owner / operator
Renewable Design & Development Limited
Year consented
2014
Location