West of A970, includes Tagdale Hill, Hill of Dale, Mossy Hill and Bersa Hill, approx 2.4km from outskirts of Lerwick and approx 4.2km from Lerwick Harbour, Shetland, ZE2 9SB
Mossy Hill is a 46.8 MW onshore wind project in Scotland. The applicant or operator on record is Peel Wind Farms (Peel Energy). Planning permission has been granted as of May 2019 and it is awaiting construction. The determining authority is Shetland Islands, reference 2018/186/Pβ¦
Consented / Approved
Project stageConsented
PlanningJun 2018 (completed)
ConsentedMay 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2022-03-30.
Registered planning capacity; not measured generation.
Mossy Hill is a 46.8 MW onshore wind project in Scotland. The applicant or operator on record is Peel Wind Farms (Peel Energy). Planning permission has been granted as of May 2019 and it is awaiting construction. The determining authority is Shetland Islands, reference 2018/186/PPF.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
46.800 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Peel Wind Farms (Peel Energy)
Owner / operator
Peel Wind Farms (Peel Energy)
Year consented
2019
Location
West of A970, includes Tagdale Hill, Hill of Dale, Mossy Hill and Bersa Hill, approx 2.4km from outskirts of Lerwick and approx 4.2km from Lerwick Harbour, Shetland, ZE2 9SB