Morton House (Marchington) is a 6.2 MW solar farm project in West Midlands. The applicant or operator on record is Foresight Group (TGC Renewables). It is recorded as operational since March 2016. The determining authority is East Staffordshire, reference P/2015/00405.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningApr 2015 (completed)
  2. ConsentedJul 2015 (completed)
  3. ConstructionJan 2016 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-09-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

6.200 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Morton House (Marchington) is a 6.2 MW solar farm project in West Midlands. The applicant or operator on record is Foresight Group (TGC Renewables). It is recorded as operational since March 2016. The determining authority is East Staffordshire, reference P/2015/00405.

Site Schematic

SUBSTATION ? ha Β· 6.2 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)6.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperForesight Group (TGC Renewables)
Owner / operatorForesight Group (TGC Renewables)
Year consented2015
Construction started2016
Commissioned / target2016
LocationMorton House, Moreton Lane, Draycott-in-the-Clay, Ashbourne, Derbyshire, Staffordshire, DE6 5BZ
RegionWest Midlands
Coordinates52.873814Β°N, 1.7764477Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)111000

πŸ“… Project Timeline

2015-04-15
2015-07-08
2016-01-04
2016-03-24