Morfa Pingett Solar Farm

Morfa Pingett Solar Farm, Pembrey, Burry Port, Dyfed, SA16 0JE

Morfa Pingett Solar Farm is a 1.6 MW solar farm project in Wales. The applicant or operator on record is Richard Thomas and Co (Hydro) Limited. The planning application was refused. The determining authority is Carmarthenshire, reference PL/02407.…

Refused
Project stageRefused
  1. PlanningAug 2021 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2021-12-10.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.600 MW
Registered Capacity

πŸ“‹ Project Overview

Morfa Pingett Solar Farm is a 1.6 MW solar farm project in Wales. The applicant or operator on record is Richard Thomas and Co (Hydro) Limited. The planning application was refused. The determining authority is Carmarthenshire, reference PL/02407.

Site Schematic

SUBSTATION ? ha Β· 1.6 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRichard Thomas and Co (Hydro) Limited
Owner / operatorRichard Thomas and Co (Hydro) Limited
LocationMorfa Pingett Solar Farm, Pembrey, Burry Port, Dyfed, SA16 0JE
RegionWales
Coordinates51.7187746Β°N, 4.2898822Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Are they re-applying (Old REPD Ref) 7914
Solar Site Area (sqm)23000

πŸ“… Project Timeline

2021-08-19