Morfa Farm, Morfa Lane, Llantwit Major, South Glamorgan, Vale of Glamorgan, CF61 2YT
Morfa Farm is a 2 MW solar farm project in Wales. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since December 2016. The determining authority is Vale of Glamorgan, reference 2015/00782/FUL.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningJul 2015 (completed)
ConsentedNov 2015 (completed)
ConstructionOct 2016 (completed)
OperatingDec 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-05-26.
Registered planning capacity; not measured generation.
Morfa Farm is a 2 MW solar farm project in Wales. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since December 2016. The determining authority is Vale of Glamorgan, reference 2015/00782/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
2.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lightsource Renewable Energy
Owner / operator
Lightsource Renewable Energy
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Morfa Farm, Morfa Lane, Llantwit Major, South Glamorgan, Vale of Glamorgan, CF61 2YT