πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Solar Farm

Mopes Lane, Purton - Solar Farm

Hills Minerals & Waste Ltd, Mopes Lane, Purton,, Wiltshire, SN5 4HG

Mopes Lane, Purton - Solar Farm is a 20 MW solar farm project in South West. The applicant or operator on record is Spring Dev 08 Limited. Planning permission has been granted as of April 2023 and it is awaiting construction. The determining authority is Wiltshire, reference PL/2…

Consented / Approved
Project stageConsented
  1. PlanningNov 2021 (completed)
  2. ConsentedApr 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2021-12-08.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

20.000 MW
Registered Capacity

πŸ“‹ Project Overview

Mopes Lane, Purton - Solar Farm is a 20 MW solar farm project in South West. The applicant or operator on record is Spring Dev 08 Limited. Planning permission has been granted as of April 2023 and it is awaiting construction. The determining authority is Wiltshire, reference PL/2021/10405.

Site Schematic

SUBSTATION ? ha Β· 20 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)20.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSpring Dev 08 Limited
Owner / operatorSpring Dev 08 Limited
Year consented2023
LocationHills Minerals & Waste Ltd, Mopes Lane, Purton,, Wiltshire, SN5 4HG
RegionSouth West
Coordinates51.5977435Β°N, 1.8746238Β°W

Additional published register fields

Registered technologySolar Photovoltaics
CfD Allocation RoundAR5
CfD Capacity (MW)20
Mounting Type for SolarGround
Solar Site Area (sqm)237000

πŸ“… Project Timeline

2021-11-03
2023-04-15