Mop End Farm, Mop End Lane - Battery Energy Storage

Mop End Farm, Mop End Lane, Mop End, Amersham, Buckinghamshire, HP7 0QP

Mop End Farm, Mop End Lane - Battery Energy Storage is a 500 MW battery storage project in South East. The applicant or operator on record is Sandbrook Capital Bes Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Bucking…

In Planning
Project stageIn planning
  1. PlanningAug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2025-09-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

500.000 MW
Power Capacity

πŸ“‹ Project Overview

Mop End Farm, Mop End Lane - Battery Energy Storage is a 500 MW battery storage project in South East. The applicant or operator on record is Sandbrook Capital Bes Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Buckinghamshire, reference PL/25/2447/FA.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)500.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSandbrook Capital Bes Limited
Owner / operatorSandbrook Capital Bes Limited
LocationMop End Farm, Mop End Lane, Mop End, Amersham, Buckinghamshire, HP7 0QP
RegionSouth East
Coordinates51.6645662Β°N, 0.6650199Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-08-15