500m North Of Ceann An Ora Quarry Ardhasaig Isle Of Harris, Western Isles, HS3 3AJ
Monan Hill Wind Turbines is a 1.5 MW onshore wind project in Scotland. The applicant or operator on record is North Harris Trust. It is recorded as operational since March 2015. The determining authority is Na h-Eileanan Siar, reference 06/00290/FUL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningMay 2006 (completed)
ConsentedFeb 2008 (completed)
ConstructionJul 2014 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-03-17.
Registered planning capacity; not measured generation.
Monan Hill Wind Turbines is a 1.5 MW onshore wind project in Scotland. The applicant or operator on record is North Harris Trust. It is recorded as operational since March 2015. The determining authority is Na h-Eileanan Siar, reference 06/00290/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.500 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
North Harris Trust
Owner / operator
North Harris Trust
Year consented
2008
Construction started
2014
Commissioned / target
2015
Location
500m North Of Ceann An Ora Quarry Ardhasaig Isle Of Harris, Western Isles, HS3 3AJ