Moat Lane, Wickerlsey, Rotherham, South Yorkshire, S66 1DZ
Moat Lane, Wickersley - Battery Storage Facility is a 100 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Storage. Planning permission has been granted as of November 2025 and it is awaiting construction. The determining aβ¦
Consented / Approved
Project stageConsented
PlanningFeb 2024 (completed)
ConsentedNov 2025 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2025-12-09.
Registered planning capacity; not measured generation.
Moat Lane, Wickersley - Battery Storage Facility is a 100 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Harmony Energy Storage. Planning permission has been granted as of November 2025 and it is awaiting construction. The determining authority is Rotherham, reference RB2024/0321.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
100.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Harmony Energy Storage
Owner / operator
Harmony Energy Storage
Year consented
2025
Location
Moat Lane, Wickerlsey, Rotherham, South Yorkshire, S66 1DZ