Moat Farm - Solar Farm is a 49.9 MW solar farm project in South West. The applicant or operator on record is Elgin Energy EsCo Limited. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authority is Forest of Dean, reference P206…

Consented / Approved
Project stageConsented
  1. PlanningJan 2022 (completed)
  2. ConsentedMay 2026 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-06-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Registered Capacity

πŸ“‹ Project Overview

Moat Farm - Solar Farm is a 49.9 MW solar farm project in South West. The applicant or operator on record is Elgin Energy EsCo Limited. Planning permission has been granted as of May 2026 and it is awaiting construction. The determining authority is Forest of Dean, reference P2061/21/FUL.

Site Schematic

SUBSTATION ? ha Β· 49.9 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElgin Energy EsCo Limited
Owner / operatorElgin Energy EsCo Limited
Year consented2026
LocationMoat Farm Newent, Gloucestershire, GL18 1JG
RegionSouth West
Coordinates51.9183363Β°N, 2.3890208Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)820400

πŸ“… Project Timeline

2022-01-25
2026-05-19