πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Minety South - Battery Storage

Land South of Minety Substation Minety, Wiltshire, SN16 9RP

Minety South - Battery Storage is a 49.99 MW battery storage project in South West. The applicant or operator on record is Statera Energy. It is recorded as operational since October 2022. The determining authority is Wiltshire, reference 17/03941/FUL.…

Operational Β· Since 2022
Project stageOperating
  1. PlanningMay 2017 (completed)
  2. ConsentedSep 2017 (completed)
  3. Construction (completed)
  4. OperatingOct 2022 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-08-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.990 MW
Power Capacity
2022
Commissioned

πŸ“‹ Project Overview

Minety South - Battery Storage is a 49.99 MW battery storage project in South West. The applicant or operator on record is Statera Energy. It is recorded as operational since October 2022. The determining authority is Wiltshire, reference 17/03941/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.990 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperStatera Energy
Owner / operatorStatera Energy
Year consented2017
Commissioned / target2022
LocationLand South of Minety Substation Minety, Wiltshire, SN16 9RP
RegionSouth West
Coordinates51.6014691Β°N, 1.9881703Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-05-05
2017-09-28
2022-10-01