OS Ref 464762 159811 Minchens Lane Bramley, Hampshire, RG26
Minchens Lane Battery Storage Facility is a 100 MW battery storage project in South East. The applicant or operator on record is Penso Power (BW ESS). It is recorded as operational since February 2025. The determining authority is Basingstoke and Deane, reference 21/00349/FUL.β¦
OperationalΒ· Since 2025
Project stageOperating
PlanningJan 2021 (completed)
ConsentedOct 2021 (completed)
Construction (completed)
OperatingFeb 2025 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2026-03-09.
Registered planning capacity; not measured generation.
Minchens Lane Battery Storage Facility is a 100 MW battery storage project in South East. The applicant or operator on record is Penso Power (BW ESS). It is recorded as operational since February 2025. The determining authority is Basingstoke and Deane, reference 21/00349/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
100.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Penso Power (BW ESS)
Owner / operator
Penso Power (BW ESS)
Year consented
2021
Commissioned / target
2025
Location
OS Ref 464762 159811 Minchens Lane Bramley, Hampshire, RG26