Battery Storage

Meteor Business Park

Unit 4, Hangar Meteor Business Park, Cheltenham Road East, Gloucester, Gloucestershire, Gloucestershire, GL2 9QL

Meteor Business Park is a 1.5 MW battery storage project in South West. The applicant or operator on record is Safran Landing Systems. It is recorded as operational since January 2020. The determining authority is Tewkesbury, reference 19/00093/FUL.…

Operational Β· Since 2020
Project stageOperating
  1. PlanningFeb 2019 (completed)
  2. Consented (completed)
  3. ConstructionApr 2019 (completed)
  4. OperatingJan 2020 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2020-01-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.500 MW
Power Capacity
2020
Commissioned

πŸ“‹ Project Overview

Meteor Business Park is a 1.5 MW battery storage project in South West. The applicant or operator on record is Safran Landing Systems. It is recorded as operational since January 2020. The determining authority is Tewkesbury, reference 19/00093/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.500 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSafran Landing Systems
Owner / operatorSafran Landing Systems
Construction started2019
Commissioned / target2020
LocationUnit 4, Hangar Meteor Business Park, Cheltenham Road East, Gloucester, Gloucestershire, Gloucestershire, GL2 9QL
RegionSouth West
Coordinates51.8965129Β°N, 2.1711911Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2019-02-21
2019-04-19
2020-01-16