πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Melton Waste Park

Land South West Of Melton Wast, Gibson Lane, Melton, North Ferriby,, Humberside, HU14 3HH

Melton Waste Park is a 22 MW bioenergy / waste project in Yorkshire and Humber. The applicant or operator on record is Transwaste Recycling & Aggregates Limited. Planning permission has been granted as of February 2019 and it is awaiting construction. The determining authority is…

Consented / Approved
Project stageConsented
  1. PlanningApr 2018 (completed)
  2. ConsentedFeb 2019 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-03-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

22.000 MW
Registered Capacity

πŸ“‹ Project Overview

Melton Waste Park is a 22 MW bioenergy / waste project in Yorkshire and Humber. The applicant or operator on record is Transwaste Recycling & Aggregates Limited. Planning permission has been granted as of February 2019 and it is awaiting construction. The determining authority is East Riding of Yorkshire, reference 18/00703/CM.

πŸ”§ Technical Specifications

Capacity (MW)22.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperTranswaste Recycling & Aggregates Limited
Owner / operatorTranswaste Recycling & Aggregates Limited
Year consented2019
LocationLand South West Of Melton Wast, Gibson Lane, Melton, North Ferriby,, Humberside, HU14 3HH
RegionYorkshire and Humber
Coordinates53.723672Β°N, 0.5312741Β°W

Additional published register fields

Registered technologyEfW Incineration
Are they re-applying (Old REPD Ref) 973

πŸ“… Project Timeline

2018-04-10
2019-02-28