Land South West Of Melton Waste, Gibson Lane, Melton, North Ferriby,, Humberside, HU14 3HH
Melton Waste Park is a 5 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Seneca Global Energy. It is recorded as operational since March 2017. The determining authority is East Riding of Yorkshire, reference 14/03951/STPLFE.β¦
OperationalΒ· Since 2017
Project stageOperating
PlanningFeb 2015 (completed)
ConsentedApr 2015 (completed)
ConstructionJun 2016 (completed)
OperatingMar 2017 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2017-06-21.
Registered planning capacity; not measured generation.
Melton Waste Park is a 5 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Seneca Global Energy. It is recorded as operational since March 2017. The determining authority is East Riding of Yorkshire, reference 14/03951/STPLFE.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
5.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Seneca Global Energy
Owner / operator
Seneca Global Energy
Year consented
2015
Construction started
2016
Commissioned / target
2017
Location
Land South West Of Melton Waste, Gibson Lane, Melton, North Ferriby,, Humberside, HU14 3HH