πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Other Registered Technology

Melton Ross

Melton Ross Quaries, Melton Ross, Barnetby,, Humberside, DN38 6AE

Melton Ross is a 5.8 MW other registered technology project in Yorkshire and Humber. The applicant or operator on record is Singleton Birch / Energos. The scheme is currently in the planning system, submitted June 2010. The determining authority is North Lincolnshire, reference W…

Revised
Project stageSuperseded by a new application
  1. PlanningJun 2010 (completed)
  2. Superseded by a new application (project stopped here)
  3. ConsentedSep 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2015-07-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.800 MW
Registered Capacity

πŸ“‹ Project Overview

Melton Ross is a 5.8 MW other registered technology project in Yorkshire and Humber. The applicant or operator on record is Singleton Birch / Energos. The scheme is currently in the planning system, submitted June 2010. The determining authority is North Lincolnshire, reference WD/2010/0704.

πŸ”§ Technical Specifications

Capacity (MW)5.800 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSingleton Birch / Energos
Owner / operatorSingleton Birch / Energos
Year consented2010
LocationMelton Ross Quaries, Melton Ross, Barnetby,, Humberside, DN38 6AE
RegionYorkshire and Humber
Coordinates53.5856697Β°N, 0.3641126Β°W

Additional published register fields

Registered technologyAdvanced Conversion Technologies
Are they re-applying (New REPD Ref)5347
Are they re-applying (Old REPD Ref) 955

πŸ“… Project Timeline

2010-06-25
2010-09-14