Meece Landfill is a 1.3 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Thomas Graveson Ltd. It is recorded as operational since February 1999. The determining authority is Stafford.…

Operational Β· Since 1999
Project stageOperating
  1. PlanningApr 1996 (completed)
  2. ConsentedMar 1997 (completed)
  3. Construction (completed)
  4. OperatingFeb 1999 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2005-06-29.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.300 MW
Registered Capacity
1999
Commissioned

πŸ“‹ Project Overview

Meece Landfill is a 1.3 MW bioenergy / waste project in West Midlands. The applicant or operator on record is Thomas Graveson Ltd. It is recorded as operational since February 1999. The determining authority is Stafford.

πŸ”§ Technical Specifications

Capacity (MW)1.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperThomas Graveson Ltd
Owner / operatorThomas Graveson Ltd
Year consented1997
Commissioned / target1999
LocationWestgate, Swynnerton, Nr Stone, Staffordshire, Staffordshire
RegionWest Midlands
Coordinates52.9023366Β°N, 2.2185013Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1996-04-01
1997-03-24
1999-02-24