πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Medway One - Energy Hub

Former Kingsnorth Power Station, Eschol Road, Hoo St Werburgh, Rochester, Kent, ME3 9NQ

Medway One - Energy Hub is a 49.9 MW bioenergy / waste project in South East. The applicant or operator on record is Low Carbon Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining authority is Medway, reference MC/24/0489…

Consented / Approved
Project stageConsented
  1. PlanningMar 2024 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-07-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Registered Capacity

πŸ“‹ Project Overview

Medway One - Energy Hub is a 49.9 MW bioenergy / waste project in South East. The applicant or operator on record is Low Carbon Limited. Planning permission has been granted as of July 2024 and it is awaiting construction. The determining authority is Medway, reference MC/24/0489.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperLow Carbon Limited
Owner / operatorLow Carbon Limited
Year consented2024
LocationFormer Kingsnorth Power Station, Eschol Road, Hoo St Werburgh, Rochester, Kent, ME3 9NQ
RegionSouth East
Coordinates51.4185849Β°N, 0.5983795Β°E

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2024-03-06
2024-07-04