Meadow Lane Park and Ride is a 0.9 MW solar farm project in Eastern. The applicant or operator on record is Cambridgeshire CC / Bouygues Energies. It is recorded as under construction since March 2022. The determining authority is Huntingdonshire, reference H/5016/16/CC.…

Under Construction
Project stageUnder construction
  1. PlanningApr 2017 (completed)
  2. Consented (completed)
  3. ConstructionMar 2022 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2022-03-25.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

0.900 MW
Registered Capacity

πŸ“‹ Project Overview

Meadow Lane Park and Ride is a 0.9 MW solar farm project in Eastern. The applicant or operator on record is Cambridgeshire CC / Bouygues Energies. It is recorded as under construction since March 2022. The determining authority is Huntingdonshire, reference H/5016/16/CC.

Site Schematic

SUBSTATION ? ha Β· 0.9 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)0.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCambridgeshire CC / Bouygues Energies
Owner / operatorCambridgeshire CC / Bouygues Energies
Construction started2022
LocationPark and Ride Site, The Meadow, Meadow Lane, St Ives, Cambridgeshire, PE27 4LG
RegionEastern
Coordinates52.3222509Β°N, 0.0652843Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID7055
Mounting Type for SolarGround

πŸ“… Project Timeline

2017-04-07
2022-03-25