Maybrook Road - Battery facility is a 13.1 MW battery storage project in West Midlands. The applicant or operator on record is Conrad Energy (Develeopments) Limited. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority …

Consented / Approved
Project stageConsented
  1. PlanningMar 2022 (completed)
  2. ConsentedAug 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-04-19.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

13.100 MW
Power Capacity

πŸ“‹ Project Overview

Maybrook Road - Battery facility is a 13.1 MW battery storage project in West Midlands. The applicant or operator on record is Conrad Energy (Develeopments) Limited. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority is Birmingham, reference 2022/01927/PA.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)13.100 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperConrad Energy (Develeopments) Limited
Owner / operatorConrad Energy (Develeopments) Limited
Year consented2022
LocationMaybrook Business Park - Unit 6 Maybrook Road Sutton Coldfield, West Midlands, B76 1AL
RegionWest Midlands
Coordinates52.5295866Β°N, 1.7883391Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2022-03-07