Land South Of Manor Farm Green End Pertenhall Bedfordshire, Bedfordshire
Manor Farm - Pertenhall is a 15 MW solar farm project in Eastern. The applicant or operator on record is Prosolia UK. It is recorded as operational since October 2015. The determining authority is Bedford, reference 14/00986/MAF.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningMay 2014 (completed)
ConsentedNov 2014 (completed)
ConstructionSep 2015 (completed)
OperatingOct 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-01-04.
Registered planning capacity; not measured generation.
Manor Farm - Pertenhall is a 15 MW solar farm project in Eastern. The applicant or operator on record is Prosolia UK. It is recorded as operational since October 2015. The determining authority is Bedford, reference 14/00986/MAF.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
15.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Prosolia UK
Owner / operator
Prosolia UK
Year consented
2014
Construction started
2015
Commissioned / target
2015
Location
Land South Of Manor Farm Green End Pertenhall Bedfordshire, Bedfordshire